Skip to main content

Efficiency of Transformer

Introduction of Efficiency of Transformer

Transformers form the most important link between supply systems and load. Transformer’s efficiency directly affects its performance and aging. The transformer’s efficiency, in general, is in the range of 95 – 99 %. For large power transformers with very low losses, the efficiency can be as high as 99.7%. The input and output measurements of a transformer are not done under loaded conditions as the wattmeter readings inevitably suffer errors of 1 – 2%. So for the purpose of efficiency calculations, OC and SC tests are used to calculate rated core and winding losses in the transformer. The core losses depend on the transformer rated voltage,

and the copper losses depend on the currents through the transformer primary and secondary windings. Hence transformer efficiency is of prime importance to operate it under constant voltage and frequency conditions. The rise in the temperature of the transformer due to heat generated affects the life of transformer oil properties and decides the type of cooling method adopted. The temperature rise limits the rating of the equipment. The efficiency of transformer is simply given as:

efficiency calculation of the transformer
Let us define x% be the percentage of full or rated load ‘S’ (VA) and let Pcufl(watts) be the full load copper loss and cosθ be the power factor of the load. Also, we defined Pi (watts) as core loss. As copper and iron losses are major losses in the transformer hence only these two types of losses are taken into account while calculating efficiency. Then the efficiency of transformer can be written as :

Where, x2Pcufl = copper loss(Pcu) at any loading x% of full load.

The maximum efficiency (ηmax) occurs when the variable losses equal to the constant losses. Since the copper loss is load dependent, hence it is a variable loss quantity. And the core loss is taken to be the constant quantity. So the condition for maximum efficiency is :
Now we can write maximum efficiency as :

This shows that we can obtain maximum efficiency at full load by proper selection of constant and variable losses. However, it is difficult to obtain maximum efficiency as copper losses are much higher than the fixed core losses.

The variation of efficiency with loading can be represented by figure below :
variation of efficiency with increase in loading

We can see from the figure that the maximum efficiency occurs at unity power factor. And the maximum efficiency occurs at same loading irrespective of power factor of the load.


https://www.bikayi.com/maatarini20

All Day Efficiency of Transformer

It is an energy-based efficiency calculated for distribution transformers. Unlike power transformer which is switched in or out depending on the load handled by it, a distribution transformer loading continuously fluctuates for 24 hours a day. As core losses are independent of load, the all-day efficiency depends on the copper losses.We define it as the ratio of output energy delivered to input energy for a 24 hour cycle. High energy efficiencies are achieved by restricting core flux densities to lower values (as the core losses are dependent on flux density) by using relatively larger cross-section or larger iron/copper weight ratio.


Comments

Popular posts from this blog

concrete pole specification | how to calculate cement, sand and aggregate quantity in concrete

Today I will tell, how PCC pole concreting is done? Before knowing about our topic, let's take a little knowledge about PCC Polls.full form of pcc pole is Plain  Cement Concrete pole .There are various types of PCC Pole like 8 mtr 8.5 mtr ,9 mtr .but Now I will discuss about only 8.5 mtr pcc pole. As per Guaranteed Technical Perticulars(GTP) Total Length-8.5 mtr Pit depth-1.5 mtr Working load applied 300 mm from top-180 kg Weight of the pole-415 Kg. Top dimension-90mmx145 mm Bottom dimensions-90mm x 300 mm we have to maintain pit length is 1.5 mtr and pole should be inside pit is L/6 where L is length of the pole. Explained : L=8.5 mtr Pit depth=L/6+0.075(Base plate) Pit diameter =20 inch(0.508 mtr) Let's go to our topic now. How to calculate cement, sand and aggregate quantities for ratio 1:2:4 Pit Size For one cmt cement required -6 bag Our pit volume (dia-0.508 mtr where r-0.254, depth-1.5 mtr) Volume -pie*r2*h                =3.14*0.254*0...

what are the possible causes of cable faults?

नमस्कार मित्रों,आज मैने HT AB CAble फॉल्ट कियुं होता है उसिके बारे में चर्चा करूंगा।    आप सभी जानते है कि एचटी एबीसी साइट इंजीनियर के लिए सरदर्दी बन जाती है। जैसे ही लाइन चार्ज करते है कुछ मिनटों या महीनों के बाद फॉल्ट आना पैदा करदेता है।   बहुत सारे इंजीनियर तो बोलना शुरू कर देते है कि खराब इनसुलेशन की बजहा से ऐसे फॉल्ट होता है।  बहुत सारे रिसर्च और अनुभव के बाद  बाद में यही नतीजे में पहुंचा कि जो इस्प्रकर की। 1) अन लोडिंग,स्टोरेज और हैंडलिंग सही से होना चाहिए। 2) टर्मिनेशन किट या ज्वाइंटिंग सही से होना चाहिए। 3) एआर्थिंग सही से होनी चाहिए जैसे कि टर्मिनल की latches  एआर्थिग  जरूर करना होता है। एक चीज ध्यान देना कि मैसेंजर तार को भी दोनों साइड में एर्थिंग करने की। ऐसे तो मैने ए भी कहूंगा कि  हर एक खंबे में मैसेंजर तार को एर्थिग करना चाहिए। Please Subscribe my YouTube channel ⁸ साइट पर केबल ड्रम की अन-लोडिंग, स्टोरेज और हैंडलिंग के लिए दिशानिर्देश जो इस प्रकार की होनी चाहिए।  केबल ड्रम की अनलोडिंग या तो क्रेन द्वारा या होइस्ट द्वारा या ट्रक ...

11KV ABC cable current carrying capacity

Let us discuss about Size and current carrying capacity of a  11 KV 3x120 mm2 AB Cable. Before getting answer we have to know about Technical Specification.The Technical Specification as below. TECHNICAL SPECIFICATION FOR 11KV AB Cable( AERIAL BUNCHED CABLES)  and XLPE insulated (CROSSED LINKED POLYETHYLENE DRY GAS CURED/WET CURED) FOR OVERHEAD LINES. 1. SCOPE  This specification covers requirements of XLPE insulated, 11 KV Aerial Bunched Cables for overhead lines. 2. COMPOSITION OF THE CABLE The composite cable shall comprise three single-core cables twisted around a bare aluminium alloy messenger wire, which will carry the weight of the cable. 3. RATED VOLTAGE The rated voltage of the cables shall be 6.35KV/11KV and the maximum operating voltage shall be 12 KV. 4. APPLICABLE STANDARDS Unless otherwise stipulated in this Specification, the following Standards shall be applicable: i) IS: 7098 (Part-II) - 1985 – Cross linked Polyethylene Insulated PVC Sheathed Cables ...