Skip to main content

How to calculate Voltage Regulation of 11 KV line

 Voltage Regulation:It is a measure of change in the voltage magnitude between sending end and receiving end of a component, such as Transmission or Distribution line.



Voltage regulation Formula:

%VR=Vs-Vr    x  100 
               Vs
Permissible Voltage Regulation in distrDistrib System:


Permissible Voltage Regulation as per REC:

Part of Distribution System

Urban Area (%)

Suburban Area (%)

Rural Area (%)

Up to Transformer

2.5

2,5

2.5

Up to Service Main

3

2

0.0

Up to Service Drop

0.5

0.5

0.5

Total

6.0

5.0

3.0

Voltage variations in 33 kV and 11kV feeders should not exceed the following limits at the farthest end under peak load conditions and normal system operation regime.

  • Above 33kV (-) 12.5% to (+) 10%.
  • Up to 33kV (-) 9.0% to (+) 6.0%.
  • Low voltage (-) 6.0% to (+) 6.0%

Sometimes it can be difficult to achieve the required voltage, especially in rural areas . Part of the reason for the high voltage drop in rural areas it due to the fact that these areas are usually further was from the electricity supplies. Therefore, the power lines have to be extended over long distances, resulting in higher line losses. Power theft is a further factor which can contribute to voltage drops in rural areas. In these cases, 11/0.433 kV may be used in place of normal 11/0.4 kV distribution transformers .


Method to calculate % Voltage Regulation:

Method -1(Distance base )

Voltage Drop  = ( (√3x(RCosΦ+XSinΦ)x I ) / (No of Conductor/Phase x1000))x Length of Line

Method-2(Load base):

% Voltage Regulation =(I x (RcosǾ+XsinǾ)x Length ) / No of Cond.per Phase xV (P-N))x100
P-phase
N-neutral

Explained:

Calculate Voltage drop and % Voltage Regulation at Trail end of following 11 KV Distribution system , System have ACSR DOG Conductor (AI 6/4.72, GI7/1.57),Current Capacity of ACSR Conductor =205Amp,Resistance =0.2792Ω and Reactance =0 Ω, Permissible limit of % Voltage Regulation at Trail end is 5%.







Method 1:

Voltge drop at Load A

  • Load Current at Point A (I) = KW / 1.732xVoltxP.F
  • Load Current at Point A (I) =1500 / 1.732x11000x0.8 = 98 Amp.
  • Required No of conductor / Phase =98 / 205 =0.47 Amp =1 No
  • Voltage Drop at Point A = ( (√3x(RCosΦ+XSinΦ)xI ) / (No of Conductor/Phase x1000))x Length of Line
  • Voltage Drop at Point A =((1.732x (0.272×0.8+0x0.6)x98) / 1×1000)x1500) = 57 Volt
  • Receiving end Voltage at Point A = Sending end Volt-Voltage Drop= (1100-57) = 10943 Volt.
  • % Voltage Regulation at Point A = ((Sending end Volt-Receiving end Volt) / Sending end Volt) x100
  • % Voltage Regulation at Point A = ((11000-10943) / 11000)x100 = 0.51%
  • % Voltage Regulation at Point A =0.51 %

Voltage drop at Load B

  • Load Current at Point B (I) = KW / 1.732xVoltxP.F
  • Load Current at Point B (I) =1800 / 1.732x11000x0.8 = 118 Amp.
  • Distance from source= 1500+1800=3300 Meter.
  • Voltage Drop at Point B = ( (√3x(RCosΦ+XSinΦ)xI ) / (No of Conductor/Phase x1000))x Length of Line
  • Voltage Drop at Point B =((1.732x (0.272×0.8+0x0.6)x98) / 1×1000)x3300) = 266 Volt
  • Receiving end Voltage at Point B = Sending end Volt-Voltage Drop= (1100-266) = 10734 Volt.
  • % Voltage Regulation at Point B= ((Sending end Volt-Receiving end Volt) / Sending end Volt) x100
  • % Voltage Regulation at Point B= ((11000-10734) / 11000)x100 = 2.41%
  • % Voltage Regulation at Point B =2.41 %

Voltage drop at Load C

  • Load Current at Point C (I) = KW / 1.732xVoltxP.F
  • Load Current at Point C (I) =2000 / 1.732x11000x0.8 = 131 Amp
  • Distance from source= 1500+1800+2000=5300 Meter.
  • Voltage Drop at Point C = ( (√3x(RCosΦ+XSinΦ)xI ) / (No of Conductor/Phase x1000))x Length of Line
  • Voltage Drop at Point C =((1.732x (0.272×0.8+0x0.6)x98) / 1×1000)x5300) = 269 Volt
  • Receiving end Voltage at Point C = Sending end Volt-Voltage Drop= (1100-269) = 10731 Volt.
  • % Voltage Regulation at Point C= ((Sending end Volt-Receiving end Volt) / Sending  end Volt) x100
  • % Voltage Regulation at Point C= ((11000-10731) / 11000)x100 = 2.44%
  • % Voltage Regulation at Point C =2.44 %

Here Trail end Point % Voltage Regulation is 2.41% which is in permissible limit.

Method-2

  • Load Current at Point A (I) = KW / 1.732xVoltxP.F
  • Load Current at Point A (I) =1500 / 1.732x11000x0.8 = 98 Amp.
  • Distance from source= 1.500 Km.
  • Required No of conductor / Phase =98 / 205 =0.47 Amp =1 No
  • Voltage Drop at Point A = (I x (RcosǾ+XsinǾ)x Length ) / V (Phase-Neutral))x100
  • Voltage Drop at Point A =((98x(0.272×0.8+0x0.6)x1.5) / 1×6351) = 0.52%
  • % Voltage Regulation at Point A =0.52 %

Voltage drop at Load B

  • Load Current at Point B (I) = KW / 1.732xVoltxP.F
  • Load Current at Point B (I) =1800 / 1.732x11000x0.8 = 118 Amp.
  • Distance from source= 1500+1800=3.3Km.
  • Required No of conductor / Phase =118 / 205 =0.57 Amp =1 No
  • Voltage Drop at Point B = (I x (RcosǾ+XsinǾ)x Length ) / V (Phase-Neutral))x100
  • Voltage Drop at Point B =((118x(0.272×0.8+0x0.6)x3.3)/1×6351) = 1.36%
  • % Voltage Regulation at Point A =1.36 %

Voltage drop at Load C

  • Load Current at Point C (I) = KW / 1.732xVoltxP.F
  • Load Current at Point C (I) =2000 / 1.732x11000x0.8 = 131Amp.
  • Distance from source= 1500+1800+2000=5.3Km.
  • Required No of conductor / Phase =131/205 =0.64 Amp =1 No
  • Voltage Drop at Point C = (I x (RcosǾ+XsinǾ)x Length ) / V (Phase-Neutral))x100
  • Voltage Drop at Point C =((131x(0.272×0.8+0x0.6)x5.3)/1×6351) = 2.44%
  • % Voltage Regulation at Point A =2.44 %

Here Trail end Point % Voltage Regulation is 2.44% which is in permissible limit.

Simple and practical method to measure Voltage Regulation in a distribution system:

1St measure staring end voltage of a DTR as Vs and then trail end voltage of a DTR as Vr then Voltage Regulation easily calculated.

For Vs=(Vry+Vyb+Vrb)/3

          Vr=(Vry+Vyb+Vrb)/3

  Vry:-Phase voltage between r and y phase



How to improve Voltage Regulation in a distribution line:


1.Use of generator voltage regulators
2. Application of voltage-regulating equipment in the distribution substations;
3. Application of capacitors in the distribution substation
4. Balancing of the loads on the primary feeders
5. Increasing of feeder conductor size
6. Changing of feeder sections from single-phase to multiphase
7. Transferring of loads to new feeders
8. Installing of new substations and primary feeders
9. Increase of primary voltage level
10. Application of voltage regulators on the primary feeders
11. Application of shunt capacitors on the primary feeders

12. Application of series capacitors on the primary feeders.
13.By preventing theft Voltage Regulation can be impoved and theft can be minimized by using of insulation on Conductor.
14.Now many projects like HVDS ,IPDS running for volatage regulation improvement.
15. In these cases, 11/0.433 kV may be used in place of normal 11/0.4 kV distribution transformers .









Comments

Popular posts from this blog

what are the possible causes of cable faults?

नमस्कार मित्रों,आज मैने HT AB CAble फॉल्ट कियुं होता है उसिके बारे में चर्चा करूंगा।    आप सभी जानते है कि एचटी एबीसी साइट इंजीनियर के लिए सरदर्दी बन जाती है। जैसे ही लाइन चार्ज करते है कुछ मिनटों या महीनों के बाद फॉल्ट आना पैदा करदेता है।   बहुत सारे इंजीनियर तो बोलना शुरू कर देते है कि खराब इनसुलेशन की बजहा से ऐसे फॉल्ट होता है।  बहुत सारे रिसर्च और अनुभव के बाद  बाद में यही नतीजे में पहुंचा कि जो इस्प्रकर की। 1) अन लोडिंग,स्टोरेज और हैंडलिंग सही से होना चाहिए। 2) टर्मिनेशन किट या ज्वाइंटिंग सही से होना चाहिए। 3) एआर्थिंग सही से होनी चाहिए जैसे कि टर्मिनल की latches  एआर्थिग  जरूर करना होता है। एक चीज ध्यान देना कि मैसेंजर तार को भी दोनों साइड में एर्थिंग करने की। ऐसे तो मैने ए भी कहूंगा कि  हर एक खंबे में मैसेंजर तार को एर्थिग करना चाहिए। Please Subscribe my YouTube channel ⁸ साइट पर केबल ड्रम की अन-लोडिंग, स्टोरेज और हैंडलिंग के लिए दिशानिर्देश जो इस प्रकार की होनी चाहिए।  केबल ड्रम की अनलोडिंग या तो क्रेन द्वारा या होइस्ट द्वारा या ट्रक ...

Cable trench specification | Various type of cable trench

  Hello friends, I had told in my previous blogging that the current carrying capacity of different UG cables.Today I will tell you how the UG cable is laying and how the cable trench is done with the specification.   UG cable is very expensive, about 3-4 times expansive and also laying. But due to many reasons we have to do UG Cable. One of them is because of the reason   we have to do UG cable even after being so expensive, is density populated areas where Overhead Network cannot be used. However, the cable should be properly laid because it takes more time to find the fault than the overhead line.           Before selecting for laying UG cable, the current carrying capacity, voltage drop and short circuit current of the cable are very important factors which I had written earlier in blogging. Generally the life of the cable is 40-50 years. But Incorrect handling/laying can result in insulation damage and decreases...

concrete pole specification | how to calculate cement, sand and aggregate quantity in concrete

Today I will tell, how PCC pole concreting is done? Before knowing about our topic, let's take a little knowledge about PCC Polls.full form of pcc pole is Plain  Cement Concrete pole .There are various types of PCC Pole like 8 mtr 8.5 mtr ,9 mtr .but Now I will discuss about only 8.5 mtr pcc pole. As per Guaranteed Technical Perticulars(GTP) Total Length-8.5 mtr Pit depth-1.5 mtr Working load applied 300 mm from top-180 kg Weight of the pole-415 Kg. Top dimension-90mmx145 mm Bottom dimensions-90mm x 300 mm we have to maintain pit length is 1.5 mtr and pole should be inside pit is L/6 where L is length of the pole. Explained : L=8.5 mtr Pit depth=L/6+0.075(Base plate) Pit diameter =20 inch(0.508 mtr) Let's go to our topic now. How to calculate cement, sand and aggregate quantities for ratio 1:2:4 Pit Size For one cmt cement required -6 bag Our pit volume (dia-0.508 mtr where r-0.254, depth-1.5 mtr) Volume -pie*r2*h                =3.14*0.254*0...