Railway Crossing Permission for Electrical line Crossing Process

Today I will share some experiences on how we can get permission from railway authority for electrical line crossing.

 First we have to open following WEB site of rail bhumi crossing sewa

 https://ircep.gov.in/IR-RBCS/login.jsp

Then have to register details with asking details like name of the department, designation, adress of office,Phone no, location of crossing etc.

After filling above ,have submit plan drawing and other documents like questionnaire, estimate..

After submission of above,have to pay registration fees of amount Rs 1000/-(One Thousand Rupees) and getting registrations successfully.

When registeration successfully done,file forwarded for intimation of joint feasibility surey ,and Railway authority would fixed date for feasibility survey with Railway Officers.Then Party, who is applied application have to intimate all officer and arrange all officer to arrive same time for joint feasibility.

After Joint feasibility done,plan drawing to be prepared and getting certification from all officer to upload on WEB potal for further process.

When joint feasibility survey completed ,have to think 80% work completed.Then have to follow up all flow of file as display on portal and have to keep in mind that nothing any file pending any of the officer more than 15 days and unfortunately this happened,file will be dropped and again have to reapply file.

Again have to ensured that Digital signature available at party before registration as in most of the time DSC(Digital Signature) required on plan , Estimate etc.

At last estimate charges , Way leave charges, Supervision charges and land leased charges have to pay through online.

After successfully on line charges submitted, have to ready for agreement certification and after agreement done , illegible for receiving NOC and immediate work can be started after submission of workplan at railway authorities.

Railway authorities also prepared flow chart of total online permission as described above..















Comments

Popular posts from this blog

concrete pole specification | how to calculate cement, sand and aggregate quantity in concrete

Today I will tell, how PCC pole concreting is done? Before knowing about our topic, let's take a little knowledge about PCC Polls.full form of pcc pole is Plain  Cement Concrete pole .There are various types of PCC Pole like 8 mtr 8.5 mtr ,9 mtr .but Now I will discuss about only 8.5 mtr pcc pole. As per Guaranteed Technical Perticulars(GTP) Total Length-8.5 mtr Pit depth-1.5 mtr Working load applied 300 mm from top-180 kg Weight of the pole-415 Kg. Top dimension-90mmx145 mm Bottom dimensions-90mm x 300 mm we have to maintain pit length is 1.5 mtr and pole should be inside pit is L/6 where L is length of the pole. Explained : L=8.5 mtr Pit depth=L/6+0.075(Base plate) Pit diameter =20 inch(0.508 mtr) Let's go to our topic now. How to calculate cement, sand and aggregate quantities for ratio 1:2:4 Pit Size For one cmt cement required -6 bag Our pit volume (dia-0.508 mtr where r-0.254, depth-1.5 mtr) Volume -pie*r2*h                =3.14*0.254*0...

what are the possible causes of cable faults?

नमस्कार मित्रों,आज मैने HT AB CAble फॉल्ट कियुं होता है उसिके बारे में चर्चा करूंगा।    आप सभी जानते है कि एचटी एबीसी साइट इंजीनियर के लिए सरदर्दी बन जाती है। जैसे ही लाइन चार्ज करते है कुछ मिनटों या महीनों के बाद फॉल्ट आना पैदा करदेता है।   बहुत सारे इंजीनियर तो बोलना शुरू कर देते है कि खराब इनसुलेशन की बजहा से ऐसे फॉल्ट होता है।  बहुत सारे रिसर्च और अनुभव के बाद  बाद में यही नतीजे में पहुंचा कि जो इस्प्रकर की। 1) अन लोडिंग,स्टोरेज और हैंडलिंग सही से होना चाहिए। 2) टर्मिनेशन किट या ज्वाइंटिंग सही से होना चाहिए। 3) एआर्थिंग सही से होनी चाहिए जैसे कि टर्मिनल की latches  एआर्थिग  जरूर करना होता है। एक चीज ध्यान देना कि मैसेंजर तार को भी दोनों साइड में एर्थिंग करने की। ऐसे तो मैने ए भी कहूंगा कि  हर एक खंबे में मैसेंजर तार को एर्थिग करना चाहिए। Please Subscribe my YouTube channel ⁸ साइट पर केबल ड्रम की अन-लोडिंग, स्टोरेज और हैंडलिंग के लिए दिशानिर्देश जो इस प्रकार की होनी चाहिए।  केबल ड्रम की अनलोडिंग या तो क्रेन द्वारा या होइस्ट द्वारा या ट्रक ...

11KV ABC cable current carrying capacity

Let us discuss about Size and current carrying capacity of a  11 KV 3x120 mm2 AB Cable. Before getting answer we have to know about Technical Specification.The Technical Specification as below. TECHNICAL SPECIFICATION FOR 11KV AB Cable( AERIAL BUNCHED CABLES)  and XLPE insulated (CROSSED LINKED POLYETHYLENE DRY GAS CURED/WET CURED) FOR OVERHEAD LINES. 1. SCOPE  This specification covers requirements of XLPE insulated, 11 KV Aerial Bunched Cables for overhead lines. 2. COMPOSITION OF THE CABLE The composite cable shall comprise three single-core cables twisted around a bare aluminium alloy messenger wire, which will carry the weight of the cable. 3. RATED VOLTAGE The rated voltage of the cables shall be 6.35KV/11KV and the maximum operating voltage shall be 12 KV. 4. APPLICABLE STANDARDS Unless otherwise stipulated in this Specification, the following Standards shall be applicable: i) IS: 7098 (Part-II) - 1985 – Cross linked Polyethylene Insulated PVC Sheathed Cables ...